How long does a re-roof actually take? An honest timeline.

Day-by-day reality of a Kent re-roof, what weather does to the schedule, and the five things that add days.

The honest answer: it depends, but here are real numbers

A typical 3-bedroom semi: 4 to 6 days in good weather. A 3-bed detached: 5 to 8 days. A larger or more complex house: we'll tell you exactly in the quote.

Weather is the honest wildcard. We work in light rain (most roofing can continue in drizzle). We don't work in strong wind or heavy rain. In Kent in winter, expect the occasional weather delay of half a day. We'll build in contingency time and we communicate the moment anything changes.

Day-by-day reality of a Kent re-roof

Day 1: Strip out and inspection The first thing we do is strip the existing covering, tiles, slate, or felt, back to the bare rafters or decking. This reveals everything: rotten timber, failed fixings, cracked sarking boards, evidence of previous repair work done badly.

We inspect everything and tell you what we find. If there's rotten timber, we price the repair there and then, nothing gets hidden, nothing gets bypassed.

Days 1 to 2: Underlay and battens New breathable underlay goes down, followed by new timber battens. If the ridge and hip boards are in good condition, they stay. If not, they come out and are replaced. Getting this stage right determines how well the finished roof performs.

Days 2 to 4 (or 3 to 6): Tiling or slating The covering goes on. Whether it's concrete tile, clay, or natural slate, each course is fixed correctly, two fixings per tile minimum, hip and valley details flashed and fitted. Not rushed.

Final day: Flashings, ridging, clean-up Lead flashings are cut and fitted to chimney stacks, abutments, and dormers. Ridge tiles are mechanically fixed (not just mortar-bedded, mortar alone fails within 10 years on a modern re-roof). Site clearance and final inspection.

The five things that add days

1. Rotten timber A single rotten rafter: add half a day. Multiple rotten rafters across a large section: add 1 to 3 days. We price this separately and fairly when we find it. We always find it honestly.

2. Complex rooflines Hips, valleys, dormers, flat sections, abutments, each adds complexity and time. A simple gable-end roof is fast. A house with a conservatory roof joining the main house, multiple dormers, and a chimney stack takes longer. We account for this in the quote.

3. Tall buildings or difficult access A four-storey property needing a special scaffold adds time and cost. Access over a neighbour's land requires a licence agreement. We factor these in during the survey, no surprises.

4. Material delays For standard concrete tile: rarely a problem. For matched natural slate or a specific clay tile to fit an existing profile: allow time for material sourcing. We order in advance and flag this clearly.

5. Weather Kent averages more workable days than most of England but not all of them. We plan for 1 to 2 weather days on any re-roof and keep you updated.

What we don't do

We don't tarp and go home for the weekend with a half-stripped roof. Every night we leave the property weatherproof, either partially complete or tarped properly with secured edges. If you're in the property during the re-roof, you'll hear us early and have the place clean before we leave.

How to get a timeline for your roof

Use the free assessment form, tell us your property type and location. We'll survey it and give you a realistic, weather-adjusted timeline in writing.

Common questions

How long does a re-roof take on a 3-bed semi?
Typically 4 to 6 working days in good weather. We'll confirm the exact timeline in your written quote.
Do you work in the rain?
Light drizzle: yes. Heavy rain or strong wind: no. We keep you updated and never leave the roof exposed overnight.
Will the inside stay dry during the re-roof?
Yes, we tarp overnight and work in sections. You won't get water ingress during the project if we manage the programme correctly.
What happens if you find rotten timber?
We stop, show you what we've found, price the repair, and wait for your approval before proceeding. Nothing gets done without your sign-off.